Qingdao Xingyue Tower participated in the design briefing of 220kV supporting transmission project of Beizhou 500kV substation in Dezhou

Views:350 Date:2018-09-02

On the morning of August 29, 2018, the 220 kV supporting transmission engineering design briefing meeting of Beizhou 500 kV substation in Dezhou was successfully held in the meeting room of Dezhou Power Supply Company of Shandong Electric Power Company. Supervisors, construction project departments, and iron tower suppliers participated, and Sun Wenzhu, deputy director of the technology research and development department, attended the meeting.


 At this meeting, the owner heard reports from all parties on the design progress, drawing delivery, construction progress, tower production and production schedule, and proposed supply requirements. This project belongs to the sixth batch of centralized bidding projects of State Grid in 2018. Xingyue Tower won a total of 5202 tons, including 693 tons of this bid section. The company will cooperate fully according to the requirements of the owner to ensure that the processing task is completed on time and with quality and quantity.